Cross-system project reporting

Know what's late, why, and what it will cost you.

Your control over a project depends on what your reports tell you. Storia’s reporting connects data across your PMIS, schedule and email, and shows the downstream impact before it hits.

One project event, tracedSample project
01Event
AconexCR-014 · Level 3 lab layout changeSubmitted 18 Jul · waiting on a decision
02Connected
  • SharePointMinutes, meetings 02 to 06 · item 4.3, carried 5 meetings
  • AconexDWG-M-204 Level 3 HVAC layout · held while CR-014 is open
  • OutlookOwner rep · Re: CR-014 lab layout change
  • AconexRFI-212 · Exhaust fan substitution
03Impact
Primavera P6IFC, lab wingOn the critical path · last schedule update 22 Apr
+73 d

Traced across 4 systems · in your next progress report

How reporting works today

Every project report starts with a picture of a crane.

Then canned exports, one system at a time, tied together by hand. Storia does that work for you.

  1. 01Follow

    It follows every project event

    An RFI, a directive, a decision in a meeting, a schedule update. As it happens, on every project.

  2. 02Connect

    It connects each event to everywhere it lives

    Your PMIS, email, minutes, contracts and schedule, linked into one audit trail across systems.

  3. 03Impact

    It shows the impact on your schedule

    Open items laid over the baseline, so you see what they will cost downstream before they do.

Reports built for your project

Three questions, answered.

Three reports clients rely on today, built from the record you already keep.

  • Progress report: who holds it?Decisions get made on time. Every action and decision from meetings, RFIs and correspondence, with an owner, a due date and the days it has waited.
  • Performance report: where do we really stand?Slippage shows up in days, not months. Milestones against your P6 or MS Project baseline, and review times for each party: owner, design firms and contractor.
  • Change analysis: where did it come from?Changes settle on evidence, not argument. Every change traced to its root cause, whether an RFI, a directive, an owner request or a site condition, with the documents behind it.
Read the full sample report →
StoriaProgress report
Cedarline Research Institute

Cedarline Research Centre

Progress report · CRC-01

Period06 Oct to 02 Nov 2026
Generated03 Nov 2026
Created byStoria Technologies
StoriaProgress report06 Oct to 02 Nov 2026

1Diagnostic

Red. The project is 73 days behind baseline. An owner decision, late design detail and slow contractor reviews hold the gap.

Overdue meeting actions
12↑ 5
As of 02 Nov · 7 on 05 Oct
Actions with no owner
3↑ 2
As of 02 Nov · 1 on 05 Oct
Longest decision waiting
108 d↑ 28 d
As of 02 Nov · 80 d on 05 Oct
IFC milestone against baseline
+73 d↑ 22 d
As of 02 Nov · +51 d on 05 Oct
Key takeawaysFinding
Decisions are the critical pathCR-014, Level 3 lab layout change, has waited 108 days for an owner decision. The lab wing IFC package cannot close without it.1
Reviews are slipping on the contractor sideContractor reviewers returned 41% of documents on time over 12 weeks. 9 documents are held past their due date.2
Created by Storia Technologies3 / 14
Sample report

Read a full sample progress report.

Fourteen pages on one fictional project, with the notes behind every number.

We send the PDF to this address.

Works inside your tools

No new tool. It works inside yours.

Get more out of the Aconex or Procore you already pay for. Storia reads the record where it lives and files the reports back there; it never replaces them.

  1. 01

    Tailored to your project

    Your reports, your meeting rhythm, your contract.

  2. 02

    Reads what you already use

    Your PMIS, schedule and email: Oracle Aconex or Procore, Primavera P6 or MS Project, Outlook and SharePoint.

  3. 03

    Delivered where you work

    Reports arrive inside your tools. No new tool to learn.

See it in a demo →
Security

Your documents stay yours.

How we handle security →
  • Data separationYour project record stays isolated from every other customer's.
  • Data residencyChoose where your data is hosted to meet your contract terms.
  • SSO and role-based accessSign in with your company SSO. Roles decide who opens what.
  • AES-256 encryptionEncrypted at rest and in transit. Your documents stay yours.

Your next delay is already in the documents.

Bring documents from a current job. We'll show you what's in them, delivered into the tools you use.